HPP Cavnic was put into operation in February 2014 and operates under a net head of 160 m and a maximum discharge of 1,9 m3/s. The flow is utilized by two identical Pelton turbines VAPHYDRO™ with 6 injectors and rated speed of 750 rpm. The rated turbine output is 1530 kW. The total installed capacity for the power plant is 3060 kW.

/uploads/project/32/thumbs/HPP_Cavnic_inline.JPG

For HPP Cavnic VAPTECH has delivered two sets of :Pelton turbine VAPTECH™, butterfly valves, hydraulic governor system, synchronous generators, digital governor & monitoring systems. This is the latest hydro project for VAPTECH in Romania.