{"id":527,"date":"2013-08-04T19:02:49","date_gmt":"2013-08-04T19:02:49","guid":{"rendered":"https:\/\/vaptech.blueberry.bg\/news\/new-prolect-alce-turkey\/"},"modified":"2013-08-04T19:02:49","modified_gmt":"2013-08-04T19:02:49","slug":"new-prolect-alce-turkey","status":"publish","type":"news","link":"https:\/\/vaptech.bg\/de\/news\/new-prolect-alce-turkey\/","title":{"rendered":"New prolect – Alce, Turkey"},"content":{"rendered":"
The project name is Alce and it is located in Turkey. The assignor is A\u0130DA Enerji San. ve Tic. Ltd. \u015eti.<\/p>\n\n\n
According to the contract VAPTECH has to deliver two sets of: turbine, inlet valve, generator, hydraulic pressure unit, automation system as well as supervision of installation works and commissioning. The delivery time for the equipment is 8 months.<\/p>\n\n\n
Alce HPP will operate under a net head of 209,2 m and a maximum discharge of 3,1 m3\/s. The flow will be utilized by two identical Pelton turbines VAPHYDRO\u2122 with 6 injectors and rated speed of 750 rpm. The rated turbine output is 2848 kW. The total installed capacity for the power plant will be 5696 kW.<\/p>","protected":false},"excerpt":{"rendered":"
On July 31, 2013 VAPTECH has signed a new contract for the supply of electromechanical equipment and associated services.<\/p>","protected":false},"featured_media":0,"template":"","meta":{"_acf_changed":false,"inline_featured_image":false},"class_list":["post-527","news","type-news","status-publish","hentry"],"acf":[],"yoast_head":"\n