In July 2015 Alçe hydropower plant was put into operation
TG units of HPP Alçe
Alçe hydropower plant is located in Turkey – one of the most potential markets in the Hydro Power sector. This is VAPTECH’ latest successfully accomplished project in Turkey after HPP Yeşılköy, HPP Guneyyaka, HPP Cigdem.
HPP Alçe operates under a net head of 209,2 m and a maximum discharge of 3,1 m3/s. The flow is utilized by two vertical Pelton turbines VAPHYDRO™ at a rated speed of 750 rpm. The total installed capacity for the power plant is 5,7 MW.
For this project VAPTECH has designed and produced also two sets of butterfly valves DN700 PN28. VAPTECH delivered also 2 sets of hydraulic governor systems and synchronous generators, automation system, installation and commissioning
◊◊◊
VAPTECH ist ein weltweiter Anbieter von Ausrüstungen und Dienstleistungen für die Wasserkraft- und Metallumformungsindustrie. VAPTECH wurde 1914 gegründet und hat seinen Hauptsitz in Sofia, Bulgarien, sowie eine Produktionsstätte in Pleven, Bulgarien, mit einer Fläche von mehr als 40.000 m².
HYDRO Abteilung von VAPTECH
VAPTECH liefert komplette elektromechanische Ausrüstungen für Wasserkraftwerke mit einem Schwerpunkt auf Turbinen, die aus hocheffizienten Ventilen, Schiebern und Automatisierungssystemen bestehen. VAPTECH verfügt über mehr als 80 Jahre Erfahrung in der Herstellung von kleinen, mittleren und großen Turbinen mit einer installierten Leistung von über 8.000 MW. Die gesamte mechanische Ausrüstung von VAPTECH wird in der Produktionsstätte von VAPTECH hergestellt und getestet.