VAPTECH has successfully commissioned hydropower plant Gokboget in Turkey.
The installed capacity of HPP Gokboget is 3 MW and operates under a net head of 236,01 m and a maximum discharge of 1,52 m3/s. The flow is utilized by Pelton turbine with 6 injectors and rated speed of 750 rpm.
Within the scope of supply VAPTECH delivered spherical valve, generator, hydraulic pressure unit, automation system as well as supervision of installation works and commissioning.
TG unit of HPP Gokboget
!m[](/uploads/news/134/thumbs/SANTRAL_BİNASI_inline.JPG)HPP Gokboget turbine house
!m[](/uploads/news/134/thumbs/20141111_006-rev_inline.jpg)In hoise functional tests of spherical valve for HPP Gokboget
◊◊◊
VAPTECH es un proveedor mundial de equipos y servicios para las industrias hidroeléctrica y de conformado de metales. Fundada en 1914, VAPTECH tiene su sede en Sofía, Bulgaria, así como su planta de producción en Pleven, Bulgaria, ubicada en más de 40.000 metros cuadrados.
HYDRO división de VAPTECH
VAPTECH delivers complete electromechanical equipment for hydropower plants with a main focus on turbines consisting of highly efficient: valves, gates and automation systems. VAPTECH has more than 80 years of experience in the production of small, medium and large turbines with a delivery of over 8,000 MW worth of installed equipment. All of VAPTECH’ mechanical equipment is manufactured and tested in VAPTECH’ production facility.